Project timeline and dependencies

Fictional launch: dates are inclusive calendar dates, not workday estimates. A successor starts after its predecessor finishes. The gap on December 6 is intentional. The table and SVG are separate snapshots. Editing table cells does not redraw the SVG; update both sources to keep them consistent.

Task Start Finish Predecessor
T1 · Plan 2026-12-01 2026-12-02
T2 · Design 2026-12-03 2026-12-05 T1
T3 · Review 2026-12-07 2026-12-09 T2
Project timeline and dependencies Fictional launch: dates are inclusive calendar dates, not workday estimates. A successor starts after its predecessor finishes. The gap on December 6 is intentional. The table and SVG are separate snapshots. Editing table cells does not redraw the SVG; update both sources to keep them consistent. Project timeline and dependencies 12-01 12-02 12-03 12-04 12-05 12-06 12-07 12-08 12-09 T1 Plan T2 Design T3 Review 2026-12-01 → 2026-12-09